Drawing Manual

Command
Polyline
Color
----Not Applicable-----
Text
"A building" or "Dharamshala"
Details
• This name should be same as in _siteplan layer for those proposed work which are nonidentical. • When one floor plan is made for multiple propwork at that time name that Building plan as – A Building (which is the text from propwork excluding the "-" and "number" e.g.: A-1 Building and A-2 Building are two propwork in Siteplan, so when we make single floor plan for both then we name the Building polygon as "A building" • Poly line should be closed
Command
Polyline
Color
----Not Applicable-----
Text
"Ground Floor" "First floor" "Typical - 1,2,3,5 floor" or "Typical - 1-3,5 floor Plan" or "Typical - 1-3,4-10 floor Plan" "Basement floor" or "Basement - 1" or "Basement-1,2" "Terrace floor" "Ground & Parking Floor" "Parking Floor" "Service floor" "Stilt Floor"
Details

• All Polygons of _Floor layer should be drawn within the polygon of _Building

• Relevant text is mandatory within each polygon of _Floor layer

• Poly line should be closed

• If floor is used to install machinery, use word "Machine" after floor name. e.g. Floor-1 Machine, Floor-2 Machine. These floor name should be same in Section Drawing.

Command
Polyline
Color
----Not Applicable-----
Text
"Flat-101" "Flat-1006" "Shop-1" "Shop-2" "Office-1" "Office-2"
Details
• It is to be drawn within the relevant BuiltUpLine layer. (eg.: ResiBuiltUpLine/CommBuiltUpLine/SpecialUseBuiltUpline/IndBuiltUpLine) • Poly line should be closed • Each UnitBUA to be named in a relevant manner as in list • To be drawn within the Floor Polygon
Command
Polyline
Color
----Not Applicable-----
Text
"M.Bedroom" "Bedroom" "Ch. bedroom" "Living room" "Store room" "Kitchen" "Toilet" "TOI" "Attached toilet" "Comm. toilet" "Gents toilet" "Women toilet" "Passage" "Shop" "Office" "WC"
Details
• It is to be drawn within the relevant BuiltUpLine layer. (eg.: ResiBuiltUpLine/CommBuiltUpLine/SpecialUseBuiltUpline/IndBuiltUpLine) • Poly line should be closed • Each Room to be named in an applicable manner as in list • To be drawn within the Floor Polygon
Command
Polyline
Color
Terrace Parapet Wall - Color Code 224
Text
----Not Applicable-----
Details

• Poly line should be closed

• Walls should not cross over any layer or object

• To be drawn within the Floor Polygon

Command
Polyline
Color
----Not Applicable-----
Text
"D1" / "D2" / "FD" (Fire Door) / "RS" (Rolling Shutter) / "Door"/ "Entry"/ "Entrance" / "Main Door" / "Exit door" / MD "
Details
• Poly line should be closed • Each door should be named accordingly as in the list • Same name should be used for same size or type of doors
Command
Polyline
Color
----Not Applicable-----
Text
"W1" / "W2" / "FW" / "Window" / "V" (Ventilation) / "V 1" or "V1" / Ventilation
Details
• Poly line should be closed • Each Window or ventilation should be named accordingly as in the list • Same name should be used for same size or type of Windows • To be drawn within the Floor Polygon
Command
Polyline
Color
Stairs - Color 120 Stair Lobby - Color 230 Landing - Color 161 Existing-Color 170
Text

"Staircase""1 FL" / "2 FL" / "3 FL" (to indicate number of flights)"Plinth Staircase"

"Existing Staircase - R"

"Existing Staircase - NR"

Details

• Poly line should be closed for the outer staircase polygon• Each stair within the staircase polygon to be drawn using Single polyline• Stair lobby should be attached to stairs polygon• Staircase and lobby to be drawn in same layer _Staircase• To be drawn within the Floor Polygon• Stairs leading to plinth level from ground level to be indicated with text as "Plinth Staircase" • For existing Staircase in existing building please use relevant text and color

Command
Polyline
Color
Lift - Color Code 114, Lift Lobby - Color Code 112, Fire Lift - Color Code 110
Text

"Passenger lift""Fire lift" "General lift" "Goods lift""Hospital lift""Vehicular Lift" or "Car lift"For Lobby - "Lift Lobby"For lift machine room - "Lift machine room"

Details

• Poly line should be closed• Each lift should be named accordingly as per its usability• Lift lobby should be attached to a lift• Each lift should contain a Door within it. The door will be assigned to _Door layer. • Lift machine room polyline is to be drawn using Line type "Dashed"• _Lift layer would contain "Lift", "Lift Lobby" as well as "Lift machine room"• To be drawn within the Floor Polygon• Minimum dimension of Lift well 1.9 x 1.7

Command
Polyline
Color
Front – Color Code 1 Rear – Color Code 6 Left side – Color Code 5 Right side – Color Code 104
Text

"Balcony"

Details

• Poly line should be closed

• Front (Road side) Balcony – Color Code 1 

• Rear Balcony – Color Code 6

• Left side (Side 1) Balcony – Color Code 5

• Right side (Side 2) Balcony – Color Code 104 

• Identify with relevant text

• Must be drawn outside of BuiltUp line

Command
Polyline
Color
----Not Applicable-----
Text
"Archproj"
Details
• Poly line should be closed • To be drawn within the Floor Polygon
Command
Polyline
Color
----Not Applicable-----
Text
"xx.xx MT wide passage"
Details
• Poly line should be closed • Each Passage should have a center line which is to be drawn using Line type "Center" • Each Passage should be named accordingly as per its width • To be drawn within the Floor Polygon
Command
Polyline
Color
----Not Applicable-----
Text
"OTS" "CutOut"
Details
• Poly line should be closed
Command
Polyline
Color
----Not Applicable-----
Text
"Terrace"
Details
• Polyline should be closed • To be drawn within the Floor Polygon
Command
Polyline
Color
----Not Applicable-----
Text
"Slab" "Beam" "Sunk Slab"
Details
• All Polylines should be closed • To be drawn within the Section Polygon • Each Slab should have text "slab" within it • Each SunkSlab" should have text "Sunkslab" within it • Each "Beam" should have text "Beam" within it
Command
Polyline
Color
----Not Applicable-----
Text
"Plinth" "Basement floor" "Basement-1 floor" "Basement-2 floor" "Ground floor" "Floor-1" "Floor-2" OR "First","Second" "Terrace floor" "Service floor" "Refuge floor" "Stilt Floor"
Details

• Polyline should be closed

• To be drawn within the Section Polygon

• Each floor should have relevant text within it as per the list

• If floor is used to install machinery, use word "Machine" after floor name. e.g. Floor-1 Machine, Floor-2 Machine. These floor name should be same in floor plan Drawing.

Command
Polyline
Color
----Not Applicable-----
Text

"OWT" | "Over head water tank" | "OHWT" | "SWHS"

Details
• Polyline should be closed • Overhead water tank to be drawn within the Section Polygon and named accordingly
Command
Polyline
Color
----Not Applicable-----
Text

"Gr.Lvl"

Details
  • A polyline to be drawn to indicate Ground Level
  • To be drawn within the Section Polygon 
  • This layer is mandatory 
Command
Polyline
Color
----Not Applicable-----
Text
----Not Applicable-----
Details
• Polyline should be closed • This Polyline should show the builtup area for residential purpose (outline of the Floor's residential area) • Should be drawn within the Floor polyline
Command
Polyline
Color
----Not Applicable-----
Text
----Not Applicable-----
Details
• Polyline should be closed • This Polyline should show the builtup area for Commercial purpose (outline of the Floor's Commercial area) • Should be drawn within the Floor polyline
Command
Polyline
Color
----Not Applicable-----
Text
----Not Applicable-----
Details
• Polyline should be closed • This Polyline should show the builtup area for Industrial purpose (outline of the Floor's Industrial area) • Should be drawn within the Floor polyline
Command
Polyline
Color
----Not Applicable-----
Text
----Not Applicable-----
Details
• Polyline should be closed • This Polyline should show the builtup area for special purpose (outline of the Floor's special purpose area) • Should be drawn within the Floor polyline
Command
Polyline, Arc, Circle
Color
----Not Applicable-----
Text
"Ramp" For Platform - "Ramp Platform" For CarRamp - "xx.xx MT Long x.xxMT High x.xx MT Wide car Ramp" For Pedestrian Ramp - "xx.xx MT Long x.xxMT High x.xx MT Wide Pedestrian Ramp" For Slope - "Slope"
Details

• Poly line should be closed• Each Ramp or slope should have a center line which is to be drawn using Line type "Center"• Each Ramp should be named accordingly as per its use• Ramp going towards basement from Ground floor to be drawn with solid polyline on the Basement floor and dashed polyline if it is to be indicated on the Ground floor.• Ramp going towards Ground from First floor to be drawn with solid polyline on the Ground floor and dashed polyline if it is to be indicated on the First floor.• In case of multiple ramps on one floor, name the ramps such that the names are not same for both.• Ramp Level to be indicated in the Section plan. Draw a circle along with similar text as in the floor plan.• Do not show the height point in section for the dashed ramp.

Command
Polyline
Color
----Not Applicable-----
Text
----Not Applicable-----
Details
• A polyline to be drawn to indicate High Flood Level • To be drawn within the Section Polygon
Command
Polyline
Color
----Not Applicable-----
Text
"Section"
Details
  • Polyline should be closed
  • Draw the Canopy using Polyline within the Section box to rectify the canopy height.
Command
Polyline
Color
----Not Applicable-----
Text
"xx or xx.xx MT wide driveway"
Details
• Polyline should be closed • It is to be drawn within the Parking polyline
Command
Polyline
Color
----Not Applicable-----
Text
"Urinal" "Bath" "WC"
Details
• Polyline should be closed • Donot use Block or Block reference • A polygon with any shape containing a relevant text should be drawn
Command
Polyline
Color
--Not Applicable--
Text

eg. 1:1 or 1:2 upto a limit of 1:20

Details
  • Polyline should be closed
  • Print Area layer to be drawn for each print you expect to be printed separately.
  • Scale is mandatory to be written with each print area.
  • The Signature block is to be drawn with Red poly line within each print block at floor/building level. The dimension of this block is based on the print ratio of that particular print area. e.g.: if print area have text 1:2 then the signature block for that print area shall be of 20x20 i.e. ratio multiplied by 10
Command
Polyline
Color
----Not Applicable-----
Text

"Existing Structure"

Details

• Polyline should be closed• A polygon to be drawn for Existing structure available on Site with a polyline.• It should contain relevant text within it.

Command
Polyline
Color
----Not Applicable-----
Text

" Refugee Area"

Details
  • Polyline must be close.
Command
Circle, Arc
Color
Red, Yellow
Text

-

Details
  • Two circles to be placed within the boundry of each  _PropWork layer.
  • One Circle will be in Red color, another will be in yellow color.
  • The placement of these circles should be such that you can get the same location within the builtup line in the floor plan as well.
Command
Polyline
Color
----Not Applicable-----
Text

"Loft"

Details
  • Poly line should be closed
  • Loft to be made within the room.
  • When Loft is shown in any floor plan then section of that particular floor plan must have height point shown using _loft layer to indicate the height of the loft.
Command
Polyline
Color
----Not Applicable-----
Text
"Title" "Elevation" "Key Plan"
Details
• Polyline should be closed • A polygon with any shape containing a relevant text should be drawn • The three polygons "Title", "Elevation", and "Key Plan" are mandatory objects.
Command
Polyline, Arc
Color
--Not Applicable--
Text

--Not Applicable--

Details
  • A polygon to be drawn in the site plan named "After amalgamation"
Command
Polyline
Color
----Not Applicable-----
Text

For Amalgamation Siteplan - "Before amalgamation", "After amalgamation"

For Sub-Division Siteplan - "Before SubDivision", "After SubDivision"

Details
  •  Poly line should be closed
  • Amalgamation and Subdivision projects should contain two site plans along with text within each site plan as specified.
Command
Polyline
Color
----Not Applicable-----
Text
“Plot”
Details
• Poly line should be closed
Command
Polyline
Color
----Not Applicable-----
Text

“xx.xx MT wide ODP road”

“xx.xx MT wide Internal Road”

“xx.xx MT wide NH road”

“xx.xx MT wide SH road”

Details
• Polyline should be closed • Relevant text should be present within each main road polygon
Command
Polyline, Arc
Color
Raised COP to be drawn in color code "52"
Text

"COP 1"

If raised COP - "Raised COP @ x.xx mt height"

Details

• A single straight polyline will be considered as one side of the common plot.• Poly line should be closed• Arc can be drawn within polyline to show a curved surface• Common plot should contain text of Raised COP when the common plot is above the plinth level.

Command
Polyline
Color
----Not Applicable-----
Text
"xx.xx MT wide"
Details
• Poly line should be closed • Internal Road for residential purpose to be drawn • A center line to be drawn within each internal road using polyline with line type "Center"
Command
Polyline
Color
----Not Applicable-----
Text
"xx.xx MT wide"
Details
• Poly line should be closed • Internal Road for Non-residential purpose to be drawn • A center line to be drawn within each internal road using polyline with line type "Center"
Command
Polyline
Color
----Not Applicable-----
Text
"Tree"
Details
• Poly line should be closed
Command
Polyline, Arc
Color
--Not Applicable--
Text

"Curve"

"Curvature"

"Splay"

Details

• Polyline should be close.

• Arc should be used to show curve.

Command
Polyline
Color
--Not Applicable--
Text

eg. 1:1 or 1:2 upto a limit of 1:20

Details
  • Polyline should be closed
  • Print Area layer to be drawn for each print you expect to be printed separately.
  • Scale is mandatory to be written with each print area.
  • Please note- The space on the right side of the Site plan after drawing print Area should be kept empty.
  • The Signature block is to be drawn with Red poly line under each print block excluding the SitePlan. The dimension of this block is based on the print ratio of that particular print area. e.g.: if print area have text 1:2 then the signature block for that print area shall be of 20x20 i.e. ratio multiplied by 10
Command
Polyline
Color
----Not Applicable-----
Text
"Road widening" or "Road widening Free of cost"
Details
• If given free of cost then use the text “Road widening Free of cost” • Poly line should be closed
Command
Line
Color
Front – Color Code 1 Rear – Color Code 6 Left side – Color Code 5 Right side – Color Code 104
Text
----Not Applicable-----
Command
Polyline
Color
----Not Applicable-----
Text
"A building" or "A-1 Building" or "Dharamshala"
Details

• This name should be same in _building layer.

• When one floor plan is made for multiple (propwork) at that time name those buildings(propwork) as – A-1 Building, A-2 Building. 

• Poly line should be closed

• Any proposed work within Raised COP should be drawn using _PropWork layer and color code 12.

Command
Polyline
Color
Two stack parking - Color Code 63 , Parking beneath raised COP - Color Code 30
Text

Commercial Car parking - "CP(C)"Commercial Visitors parking - "VP(C)"Commercial two wheeler parking - "TW(C)"Commercial Loading Unloading - "LD(C)"Industrial Car parking - "CP(I)"Industrial Visitors parking - "VP(I)"Industrial two wheeler parking - "TW(I)"Industrial Loading Unloading - "LD(I)"Residential Car Parking - "CP(R)"Residential two wheeler parking - "TW(R)"Residential Visitors Parking - "VP(R)"Special Car parking - "CP(S)"Special Visitors parking - "VP(S)"Special two wheeler parking - "TW(S)"Special Loading Unloading - "LD(S)"

Details

• Poly line should be closed

• Type of parking with relevant applicable text as listed should be indicated

• Two stack parking should be drawn using color code 63.

• Two stack parking should be within the parking polygon

• It is to be drawn within Plot polygon or within any floor Polygon

• Any parking underneath the common plot should be drawn using the colorcode 30 only

Command
Polyline, Arc, Circle
Color
----Not Applicable-----
Text
Percolating Well Rain water Harvesting Under Ground Water tank Electric Substation Rain water storage tank Entrance Foyer Overhead water tank Percolating Pit Soak Pit Septic Tank LetterBox Garbage Pit Community Bin Servant Quarter Parking Garage Pump Room Well Security Room Transformer Room Meter Room Security Cabin Fire Hydrant Telephone Distribution equipment AC Plant Room Solar Heating System Generator Room Refuse Chute Office Room Swimming Pool Sump tank Sewage treatment Plant AHU Effluent treatment Plant Safe deposit Vault Fire water tank Fueling station Canopy Fueling Pedestal Storage
Details

• Poly line should be closed• Some items are listed which can be shown under Accessory layer• Write applicable text for each item shown along with its storage capacity where ever applicable• 

Fueling Pedestal / Curb Site to be drawn using Polyline within AccessoryUse layer. It should have text "Fueling Pedestal". In case of multiple Fueling Pedestal name them as "Fueling Pedestal 1", "Fueling Pedestal 2". Draw it in Site Plan within the Plot.

Fueling Station Canopy to be drawn using Polyline within AccessoryUse layer. It should have text "Fueling Station Canopy". Draw it in Site Plan within the Plot.

Command
Polyline, Arc
Color
----Not Applicable-----
Text
"Basement"
Details

• A closed area to be drawn for basement with polyline

• Poly line should be closed

•This is to be drawn for the largest basement in case of multiple levels of basement

Command
Polyline
Color
----Not Applicable-----
Text

Toilet | TOI | Parking | Open Staircase | Servant Quarter | Pump Room | Security Room | Transformer Room | Meter Room | Security Cabin | Parking Garage | AC Plant Room | Storage | Generator Room | Office Room | Safe deposit Vault

Details
  • can draw multiple elements in the same layer
  • The construction done within the margin line are to be drawn in this layer
  • Poly line should be closed
  • Some items are listed which can be shown under WithinMarginLine layer
  • Each element drawn to be assigned with some relevant text.
Command
Polyline
Color
----Not Applicable-----
Text

"Existing Structure to be Demolished"

"Existing Structure"

Details
• Polyline should be closed • A polygon to be drawn for Existing structure available on Site with a polyline. • It should contain relevant text within it.
Command
Polyline, Arc
Color
--Not Applicable--
Text

"xx" (Distinct number) or "A-1"

Details

• Polyline should be closed

• Each subplot polygon should contain distinct number or an alphabet with number

• Any subplot should not have same or duplicate name

Command
Polyline, Arc
Color
--Not Applicable--
Text

"NetPlot"

Details
  • Poly line should be closed
  • This is a mandatory layer
Command
Circle, Arc
Color
Red, Yellow
Text

-

Details
  • Two circles to be placed within the boundry of each  _PropWork layer.
  • One Circle will be in Red color, another will be in yellow color.
  • The placement of these circles should be such that you can get the same location within the builtup line in the floor plan as well.
Command
Polyline
Color
----Not Applicable-----
Text

-

Details

• Poly line should be closed

• Should be drawn within _Plot & _NetPlot boundry

Command
Polyline, Arc
Color
--Not Applicable--
Text

Distinct text for each polygon

Details
  • A polygon to be drawn in the site plan named "After Sub-Division"
  • Polygon should be closed